Oconomowoc High School East Campus construction making progress

OCONOMOWOC, Wis. (CBS 58) – Significant progress has been made on Oconomowoc High School East Campus, according to district officials.

Structural steel installation in the lower level is 95 percent complete while metal framing on the main level is 75 percent finished. Installation of the fire protection system is 80 percent complete.

District leaders also say exterior demolition is finished and window replacement has begun in areas.

Around 25-30 people are currently working on the site to ensure the project is complete for the 2018-2019 school year.